Michigan's Construction Lien Act lets contractors, subcontractors, suppliers, and laborers claim a lien on property they improved if they are not paid. Two deadlines drive most of it: a notice of furnishing within 20 days of first work, and a claim of lien recorded within 90 days of last work.
The Construction Lien Act, Public Act 497 of 1980 (MCL 570.1101 to 570.1305), creates lien rights to secure payment for labor and materials used to improve real property. For a new home, that means anyone who worked on or supplied the build may have lien rights if they are not paid.
| Document | Who and When |
|---|---|
| Notice of Commencement | Provided by the owner at the start of the project. If the owner fails to provide it within 10 days of a request, the deadline for a notice of furnishing is extended until 20 days after the notice of commencement is provided. |
| Notice of Furnishing | Served by subcontractors and suppliers within 20 days after first furnishing labor or material. Laborers serve within 30 days after unpaid wages were due. |
| Sworn Statement | The contractor's statement listing subcontractors, suppliers, and amounts owed. Owners can require one before making a payment. |
| Lien Waiver | Signed by contractors, subcontractors, and suppliers as they are paid, partially or in full. |
| Claim of Lien | Recorded with the county register of deeds within 90 days after the last furnishing of labor or material, and served within 15 days after recording. |
| Lawsuit to Enforce | Must be filed within one year after the claim of lien is recorded. |
Summary of MCL 570.1108 to 570.1111. Not legal advice.
Payments an owner makes to the contractor under a sworn statement or a waiver of lien reduce what a subcontractor or supplier can claim for work furnished before that party's notice of furnishing arrived. That is why builders, lenders, and title companies insist on complete sworn statements and waivers at each draw and at closing.
Because a claim of lien can be recorded up to 90 days after the last work, a lien can appear after a new home has closed. Before insuring a newly built home, the title company and underwriter look for complete sworn statements and lien waivers covering the work. Missing waivers are the most common reason new construction closings are delayed.
Questions about lien rights, defenses, or a specific dispute belong with a construction attorney. We handle the title and closing side.
This page summarizes Michigan requirements for general information. It is not legal advice.
How Title WRX handles draws, waivers, and new construction closings.
See Builder Closings →Call (248) 230-2670 or schedule a free consultation. We handle closings throughout Michigan.
Call Now → Book a Consultation →